HOME - DEVELOPMENTAL MILESTONES
Milestones
The development milestone of the Outside Battery Limits(OSBL) and Inside Battery Limits(ISBL) are overlapping in several phases. The development of the project commenced with soft development, which are majorly engineering designs in later 2015 and later followed with Infrastructural development. The development of the project becomes more obvious with the Infrastructural development commencing with land acquisition and land preparation in 2016.
The land preparation for the project site was the initial front charge development this lasted for over a year. The land clearing and destumping of the 19.9 hectares was for a period of 91 days and the sand-filling and reclamation campaigns with 2.7million cubic meters of sand lasted for 9months.
OSBL MILESTONES

ISBL MILESTONES